1 Year Coastville Scaffolding Project

Finally after 1 year our Coatesville Auckland scaffolding project is drawing to an end as a 200 tonne crane rolled in with spreader bars and lifting strops The tube and clip temporary roof and the walls had the shrink wrap taken off the weekend before in preparation of the scaffold dismantle Once the crane was position the temporary tube and clip scaffold beamed roof sections were ready to be dismantled in 3 separate lifts

When the 1st section was taken off we had 3 scaffolders ready to dismantle and load onto the truck in readiness for the 2nd and then finally the 3rd and last section The whole process only took 8 hrs with 6 men and the main contractor was very happy due to his expectation of nearly 2 days, a saving on crane hire and time saving on the project.

 All-scaffolding-coatsville-scaffold-projject-comp-w