 AllScaffoldingHotelBalconyRepair8

Stage 2 commenced at the central Auckland hotel this week.


This stage was a little more difficult than the last due having to erect the support and access towers off a veranda roof. So we had to look at directing the load of not only the crumbling balcony and the work men (live load ) but the scaffold (dead load ) back down to the ground.


In this case we back propped the veranda roof.


This worked exceptionally well and is in use as I write...